Bhubaneswar: A significant achievement was reached on Wednesday in the Khurda Road–Bolangir railway line initiative, with the successful completion of the 4,185-meter-long Tunnel T-4 located between Adenigarh and Charichhak stations in the Boudh district.
This accomplishment marks the longest tunnel not only within this project but also in the state of Odisha. To date, 226 kilometers of the total 301-kilometer route has been completed, stretching from Khurda Road to Daspalla on one side and from Bolangir to Purnakatak on the opposite end.
The remaining 75 kilometers, which includes seven additional tunnels, is currently under construction and is making steady progress. The successful daylighting of Tunnel T-4 represents a crucial step forward, bringing the project closer to its objective of linking Odisha's coastal areas with its western regions.
You may also like
Where 10 players Lionel Messi tipped to become superstars are now - with two at Man City
Meghan Markle 'snubbed' by Princess Eugenie after being forced to settle for second choice
Urgent warning to anyone eating chocolate Easter eggs after certain time
Kirsty Gallacher's life - divorce, famous family and finding love again
Football news: Mikel Arteta sets Arsenal contract task as Man Utd plan is made clear